Current Projects

Sheffield Community Arena, Sheffield

Client: B&E Boys Ltd

Description: Large sports arena where our works comprised of reinforced concrete ground beams, two RC concrete lift pits featuring a Visqueen tanking system, extensive drainage and services installation along with the full external hard landscaping scheme including kerbing, permeable paving, bollards and cycle stands.


Fuel Tank Installation, Lutterworth

Client: Fueltek Ltd

Description: Civil engineering works in relation to a new fuel tank installation. Included ductwork and draw chambers for supply lines, power and data, in-situ concrete base for a fuel pump island and reinforced concrete slab works.


Fuel Tank Installation, Speke

Client: Fueltek Ltd

Description: Extensive civil engineering works in relation to a new fuel tank installation. The works included a new reinforced concrete fuel tank base, two remote pump islands with containment kerbs plus the associated ductwork for supply lines, power and data. All this was carried out within a busy distribution hub.


Lidl Supermarket, Chadderton

Client: Castlehouse Construction Ltd

Description: Extension to existing store comprising of in-situ concrete ground beams, retaining walls, dock leveller ramp, reinforced concrete floor slab, new foul and surface water drainage system and hard landscaping works including kerbs, trief containment kerbs, edgings, precast concrete flags, block paving and brushed concrete slabs.


Culvert Replacement, Bacup

Client: N/A

Description: A partially collapsed culvert running beneath the site of the Former Bacup Health Centre led to a major civil engineering project on this town centre site. An entire section of the existing stone culvert had to be removed and the river temporarily diverted to allow the works to take place. DTM Groundworks Ltd installed a new sloping reinforced concrete bed to carry the river and then formed new in-situ reinforced concrete walls. Once complete the new culvert was capped off with prestressed concrete planks to completely enclose the river and allow new development on the site to take place. Bat boxes were installed within the completed culvert to encourage the species to nest. Downstream of the culvert replacement works, DTM Groundworks Ltd exposed and strengthened sections of the original stone culvert. All of this work was completed in just four weeks and without disruption to the river flow.


Car Point Sales, Rochdale

Client: Car Point Sales

Description: A collapsed stone river wall at Sudden Brook led to an unusable and unsafe site. DTM Groundworks Ltd were employed to first of all remove the remnants of the original wall and make the site safe. A cofferdam was then created to form a dry work area to enable a new concrete foundation to be installed below the water level. Next DTM Groundworks Ltd constructed a new interlocking concrete block retaining wall. The difference in levels between the river and site meant this new retaining wall had to be 5.5m high. The installation of a Tensar geogrid tied the new concrete ‘Lego’ block style wall into the 6F2 stone backfill material. A new powder coated 868 mesh fence was installed to the top of the new river wall on completion.


Froneri, Skelmersdale

Client: Castlehouse Construction Ltd

Description: New warehousing built within the exisitng manufacturibng facility. DTM carried out foundations, new drainage system including cellular retention tank with hydrobrake manhole and sheet piled retaining walls.


Jaguar / Land Rover Dealership, Nelson

Client: Davlyn Construction Ltd

Description: A prestigious new dealership on an existing site. Following extensive demolition works, DTM Groundworks have carried out new reinforced concrete foundations comprising of ground beams, pile caps and retaining walls. A complete new site-wide drainage system is being installed along with extensive services comprising of external lighting, water stand pipes, communications and CCTV systems. A completely new external works design involves in-situ concrete retaining walls, kerbs, block paving, resin-bound paving and ACO drainage channels.


Gilbraith Logistics, Blackburn

Client: Gilbraith Logistics Ltd

Description: Upgrade program involving new external reinforced concrete external hardstandings along with the maintenance of the existing drainage system. This work is being carried out in phases whilst the facility is in use.


New Projects Coming Soon

. . . . .

Our Past Projects can be found here.


DTM Groundworks Ltd - Culvert Replacement, Bacup

DTM Groundworks Ltd - Culvert Replacement, Bacup

DTM Groundworks Ltd - Culvert Replacement, Bacup

DTM Groundworks Ltd - River wall rebuilding, Rochdale

DTM Groundworks Ltd - River wall rebuilding, Rochdale

DTM Groundworks Ltd - River wall rebuilding, Rochdale

DTM Groundworks Ltd - Whinberry View, Rawtenstall

DTM Groundworks Ltd - Whinberry View, Rawtenstall

DTM Groundworks Ltd - Whinberry View, Rawtenstall

DTM Groundworks Ltd - Whinberry View, Rawtenstall